The relevant Test Report/certificate shall be enclosed along with bid. Further, design review of offered transformer shall be carried out based on the design of reference transformer, which has already been subjected to Short circuit tests in lieu of repetition of Short circuit tests. In case, manufacturer has not conducted short circuit test earlier, the same shall be carried out on offered transformer.
The supplier shall be responsible to select and verify the route, mode of transportation and make all necessary arrangement with the appropriate authorities for the transportation of the transformer.
The main tank of the transformer shall be transported on Hydraulic trailers equipped with GPS system for tracking the location of transformer at all times during transportation from manufacturer’s works to the designated site. The supplier shall intimate to Employer about the details of transporter engaged for transportation of the transformer.